Community Activity Zone

Project Manager

Kevin Cunningham
Project Manager for: 
Perth Football Club Zone, West Coast Eagles Zone and Community Activity Zone
(08) 9311 8111

Project Updates

October2019

News

Construction underway in Zone 2X

October 9, 2019

Construction is underway in Zone 2X on the former bows club site. Here you can see the beginnings of the path network and space for the courts has been laid out.

September2019

News

Zone 2 update

September 3, 2019

On Wednesday 14 August, a progress update was provided to Lathlain neighbours whose residences front onto the park on Bishopsgate Street, Goddard Street, McCartney Crescent, and Roberts Road, and also those fronting the old bowling green site on Planet Street and Bishopsgate  Street. 

The points that were shared were:

  • Lathlain Precinct Redevelopment journey kicked off in earnest in 2014.
  • Community engagement for Zone 2, Community Activity, occurred in 2016.
  • The community informed concept plan for Zone 2, including the extended area of the ex-bowling greens and Tom Wright Reserve, was approved by Council resolution in August 2017.
  • Detail design consultants were contracted in early 2018, to prepare plans and documents based upon the approved concept plans.
  • The detail design was delivered by the consultants in December that year.
  • Zone 2 and 2X works tender closed in February 2019.
  • Contract was executed and site possession made available to the contractor in June 2019.
  • Their project schedule programs to have the contracted works complete prior to Christmas 2019.
  • There will be other project activities within the zone that will follow the contracted works, such as the public art installation.

Attached is a gallery of plans taken from the tender document showing proposed works for Zones 2 and 2X.

Subscribe to RSS - Community Activity Zone